Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,639,272
Community Members
 
Community Events
196
Community Groups

How is Release Status( on track/off track) calculated?

How is Release Status( on track/off track) calculated?

We are currently using portfolio version 3.6.

 

We have 2 issues in a release, 1 in todo status and 1 in progress status, but the release end date has already passed but it still shows on track.

 

My assumption is that because the date has passed and there is still work to be done that the release would reflect off track.

1 answer

2 votes
Chiragkumar Rupani
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
Jul 25, 2019

Hi Diego,

Thanks for letting us know. The is definitely an issue and the past release shouldn't be shown as on-track. This is already in our roadmap and planned to be fixed.

Regarding how the release status (on-track/off-track) is calculated, here is the explanation.

Release status is calculated based on the target dates of any issues assigned to the release. Here are the definitions:

Released - If the release is Released (i.e. released in Jira) then it's status is not calculated. The release status is only calculated for the Unreleased releases.

On-track - If the all issues assigned to the release are starting and finishing before the release date then the release is on-track. Also if there are no issues assigned to the release or none of the issues assigned to the release has dates then also it will be on-track.

Off-track - If any of the issues is starting or ending beyond the release date then the release is off-track.

Just note that currently the issue status is not taken into account and the release status is purely calculated based on the target dates set on the issues assigned to it. We are trying to improve this behavior, so keep following the documentation.

https://confluence.atlassian.com/jiraportfolioserver/managing-releases-952623605.html

I hope this helps, let us know if you have any further questions.

Regards,

Portfolio for Jira 