Hello, Hope all of you are well. Have a client that is requesting "dependency (depends on / is dependency of) and relation (is related to) in addition to the blocker (blocks / is b...
Hi there! I have two build plan: buildplan A and buildplan B The buildplan A has a dependency - the buildplan B I mean, after the build plan A the build plan B runs H...
Hi, I find the Dependencies report very useful to quickly show dependencies between teams. However now the view is starting to get blurred by dependencies that are already closed, in closed sprints. ...
...ipeline(s). There is no out of the box update for dependency changes regarding caches. We are aware of this proposed solution regarding automatically refreshing caches upon dependecy changes, however t...
Hi, I have automation currently working which creates a list of sub-tasks with issue created as a project. The issue itself sets the start date and end date of the project. Assuming sub-tasks are co...
Hi, For JIRA Roadmaps plan in DataCenter version, how can I use 'drag and drop' to enable/show dependencies as a link between issues? Please refer to the attached snippet. If not 'drag and drop', ...
We are looking for a way to notify the user assigned to a checklist item when the prior checklist item has been completed. I've set up the command below as if the bold variables worked, but the...
We currently use the Trello board for our quarterly close process and i think it would be helpful to have the ability to show the dependencies among the cards in the Trello board so if something is l...
In our Jira instance, we have renamed our epics to features and created a new type of epic ticket. This configuration brings a new hierarchy between our tickets. Epics > Features > Ot...
...nd the dependency is concurrent, my dependency is still flagged as red when I start Story B and Story A together (or even before Story A ends). What's the major difference between sequential v...
I want to setup JIRA automation that ONLY sends out a notification when all dependencies on an issue are met. How can I do that?
How do I setup a filter using scriptrunner that will show issues with the following conditions: linkedissue is "is depended on by" changes from status of development to done or cancelled in an ac...
...ust first finish to let A start). So in a business sense, it is a dependency. Precisely, it is the Finish-to-Start (FS) dependency. It could also work the other way r...
I have created a dependency automation rule that alerts assignees of linked tickets when each ticket is marked as done or cancelled. What I want to happen is that when a team on another JIRA p...
Hi- we are running Jira DC V8.16.0. I used to be able to see dependencies in the timeline and also under the dependency tab. The feature disappeared a few months ago. Is there a plan to bring i...
How can I create an automation rule that notifies an assignee when a linked issue, that is a dependency (is depended on by or depends on), is marked done? Both between cards on the same projects or c...
...ne to another. Also all good here. However, when I try to add a depencency between two different teams/projects, the lines do not show. The dependency is created, because if I go to the source task, I c...
...ave a blocking relationship between two Stories belonging to two different Features, would Advanced Roadmaps then show that dependency also at Feature level (if it at all supports this structure).&n...
Can you track dependencies in advanced roadmaps other than blocks? We use all of the linked options and i would like to track that in my advanced roadmap.
I can do a search that returns the tickets that have dependencies. What I want to know is if the dependencies are tickets for different teams. For example: Project Acme has 3 teams, X, Y, and Z. The...
...locks - is dependent by - has dependency on The JIRA roadmap dependency management , presently capturing only the top 4 dependency types. Is there a way I can configure the JIRA roadmap to i...
Hi I've got two custom fields (datatype). I want to show additional field when some rules are complied when I create ticekt. The first rule: When date in one field is =>16'th day of mon...
...f auto-x). This all works to create the tasks etc. However, some of the tasks have a dependency on other tasks. So, Task X can't start until Task Y is complete, or Task Z can't start until subtask w i...
...cross projects by adjusting settings? Is there an add-in that can do this? I have looked at dependency mapper for JIRA and link map, but it isn't clear to me whether these can actually visualize d...
...ast the original date and exceed the due date for the epic, is there a way to make the epic update due to the dependency. The epic will no longer be able to be completed by Date 2, due to the fact t...