I would like to setup a rule that changes the date on a card to be 12 weeks away every day (or 84 days if needs to be days not weeks)
We have an events calendar so want an ongoing reminder of the date in 12 weeks time for planning purposes.
@Rick Notley you can create a scheduled automation
Action will be edit issue field
Field: due date
Value:
(This will move existing due date 84 days away.
if you want the date to set 84days from the moment when automation is triggered, you can use:
Beside using days you can use Hours, Weeks...
The synthax is the same, just replace "Days" with Weeks and change number
thanks, not sure how to implement this, what do I need to do to set this up?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sorry, i missed that you are trying to set this in Trello
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.