Hi, I want to use trello for maintenance of refrigeration and HVAC equipment. The frequency varies as to when I need to service a particular unit. In a perfect world I would complete the task on the date specified on card. However, sometimes I can be a week or two behind. So if I set a card/task for the 1st of a month but don't actually complete it until the 15th I would like the next card generated to add one month to the date the task was completed instead of saying due date is on the 1st again. Is this possible? Thanks
@Marco_Nieto I created this exact same thing for my house: things have maintenance periods, and if you don't get to it right on the due date, the next maintenance period should be X days away from today, not from the previous due date. You can use Butler for this:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.