Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,456,776
Community Members
 
Community Events
176
Community Groups

Team-managed Kanban - how do I hide older Done tickets?

I see plenty of articles and forum entries from admin managed and older versions of Jira Kanban boards for how to limit how many tickets the Done column displays by how old the ticket it, but I don't see how to do this for the new team-managed version of the Kanban board. 

 

Does anyone know if that's something that is possible in this version? It's for a marketing team, so version-based hiding won't be applicable. This is in my view a key feature of any Kanban board that doesn't want to become a swamp, so I'm very interested in knowing how to achieve this. Any help would be really appreciated.

1 answer

1 accepted

1 vote
Answer accepted
Trudy Claspill Community Leader Apr 08, 2022

Team Managed projects do not include the feature to let you configure the age for hiding done issues. It is hard-coded to hide done issues when they have been done for two weeks or longer.

You can, however, manually clear the issues from the Done column. Refer to this article

https://community.atlassian.com/t5/Jira-articles/Introducing-manual-board-clearing-for-your-next-gen-Kanban-board/ba-p/1411958#M1379

I'm still looking to see if I can find an already existing Atlassian backlog item for being able to set the age used to hide done issue in the kanban board for a Team Managed project.

Thank you so much @Trudy Claspill ! This has really helped me. I do think it's odd that they made this hardcoded, I guess it's taking this whole "simplified" thing to a new level, but they need to take care that simplified doesn't turn into mystified XD

I was going crazy looking for this option but you have answered the question so at least now I know what I am working with, I really appreciate it.