Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,455,376
Community Members
 
Community Events
175
Community Groups

Gantt dates are not synced to the start/end sprint dates

I have a detailed project structure including time estimations for all stories and start/end dates for all sprints, but when i create a Gantt using Structure tool all my sprint dates are not synced

1 answer

1 vote

Hello @Yevgeny Alshitz ,

David from ALM Works here.  

Have you adjusted the Gantt Configuration to Use Sprints for Manual Scheduling?

If not, the linked documentation should help get you started.

Best,
David 

Hi

Most of my sprints are starting from project start date on the Gantt although all sprints start and end dates are well defined on the backlog.

Why there is no sync between backlog and Gantt?

Hello @Yevgeny Alshitz ,

Did you have a chance to review the documentation I linked previously?  It describes how to use Sprints for scheduling in the Gantt chart.

Best,
David

Like Dave Rosenlund _Tempo_ likes this

Yes, but i didn't find anything that can fix the issue

Hello @Yevgeny Alshitz ,

Please reach out to our support team directly via support@almworks.com or through the customer portal support.almworks.com.

We will be happy to review your set up and provide additional guidance.

Best,
David