Why does closing issues turn the bar yellow?

Luke Dyer February 19, 2012

When we close out an issue, the bar turn yellow and says all of our issues are in progress when they are actually done. What are we doing wrong?

2 answers

1 accepted

0 votes
Answer accepted
Renjith Pillai
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 19, 2012

Is the column configuration, (either in Task Board or Rapid Board) having the status 'Closed' mapped to 'In Progress' column?

Luke Dyer February 20, 2012

Hi - Thanks you for your response! No - the task board shows Closed mapped to Done and we do not have the Rapid View set up.

0 votes
Adam Saint-Prix
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
February 20, 2012

Are you setting a resolution on the closed tickets? If there is not a resolution set, I think GH will show the ticket as 'In Progress'. These scenarios are especially likely if you've created your own workflow from scratch.

Other ways to tell you have this problem (no resolution):

1) The ticket still shows up on the current assignee's Assigned to Me list

2) Issue navigator search results show status "Closed" with resolution Unresolved.

I'd check that next.