What is the formula behind the Σ Progress?

What is the formula behind the Σ Progress?

5 answers

Effective Work (EW) = sum(time logged)

Estimated To Completion (ETC) = Time Remaining = Estimate - EW

Now, the tricky part: The estimate is either EAC (Estimate At Completion = Original Estimate) or Adjusted Estimate At Completion (EW + Remaining)

sum progress is MIN(percent of EW in Estimate, 100)


Hope I get it right.

What product are you referring to?

Obviously: +

@ Renjith V, Jira, GreenHopper

Based on the valuse we update in Original Estimate; Remaining Estimate;Time Spent how the Σ Progress been computed?

@ Renjith V, I am using the Jira/GreenHopper

Hello!

For any calculations in Confluence, including any manipulations with table data, you may use CelesteCS Math for Confluence.

Assume you have a table with three columns and three rows on your page – from A1 till C3, where row 1 is the header row. The sum calculation formula for rows 2 and 3 will be simple:

SUM(Table1.A2:C3)

There is a plenty of other functions in the macro, so you may perform any calculations using formulas in EXCEL style.

Thanks!

 

Suggest an answer

Log in or Sign up to answer
Community showcase
Published 11 hours ago in Jira Ops

Jira Ops Early Access Program Update #1: Announcing our next feature and a new integration

Thanks for signing up for Jira Ops! I’m Matt Ryall, leader for the Jira Ops product team at Atlassian. Since this is a brand new product, we’ll be delivering improvements quickly and sharing updates...

158 views 0 5
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you