Unable to Complete a Sprint with Open Sub Tasks

Here's one for the Greenhopper Guru's out there. I'm trying to close our most recent Sprint, however it is blocking due to some Sub-Tasks not being complete.

This is normally fine, they're typically supporting tasks that haven't been completed. But I'm going through the list of issues that Greenhopper indicates as causing issues and it's also complaining about Issues which haven't even started, or are In-Progress. Previously Greenhopper would have simply shifted these over to the next Sprint, but this time it's blocking the Sprint entirely.

Any clues would be great!

1 answer

1 accepted

Finally found the issue after having a dig around in Support. Looks like a bug in the version of OnDemand that was released this Monday (15th July 2013)

You can also find related conversation at https://answers.atlassian.com/questions/190546/can-no-longer-carryover-incomplete-stories-getting-sprint-cannot-be-completed-as-there-are-incomplete-subtasks?page=1#190978

We're working on scheduling the fix and any updates will be in the bug report you referenced.



Suggest an answer

Log in or Join to answer
Community showcase
Jason Wong
Published yesterday in Agility Beta

Welcome to agility

Every team in the world is unique, and so   Atlassian believes   that each and every team's best way of working  needs to  be molded to their unique circumstances  – ...

250 views 5 14
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot