Tempo Folio. Why is SPI calculated based on distributed the Total planned costs linearly over the Folio time frame?

Before Folio version 10 SPI was based on Planned Cost to date (no linear distributing). Why was it changed?

Can the method of calculation be configured?

 

1 answer

Hi,

You are right, in the previous versions, the SPI was based on the planned value not linearly distributed.
After some clients feedback and revising the SPI formula, we had to readjust the computation of it to be based on the linear planned value. We needed to conform with the PMI formula.

Unfortunately the computation of the indexes is not configurable now a day but I could surely add a feature requests for this.

Warm Regards,
JC

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Posted Thursday in Off-topic

Friday Fun: Magic Eyes

...staring into the background. Once the image pops out in 3D, you can look around the picture and enjoy. If you will see if you are a true illusion master! :) You did it? :) Wow! Awesome! As a bonus...

418 views 79 11
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you