Similarity of Component with Backlogs

This question is in reference to Atlassian Documentation: What is a Project

In Agile Sprint methodology, the requirements are stated as backlog items.

Each sprint, some of this backlog items are selected for development, so they become sprint backlog items.

So can we assume that each component within a project can be considered as a backlog?

and the issues as task breakdowns for implementing each sprint backlog item/ 

1 answer

0 votes

No.

A component is a way of showing that an issue is related to a specific part (or several parts) of the project.  A backlog is a list of issues you need to deal with.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published 3 hours ago in Agile

How Scrum works? It starts with training and education

To answer “How scrum works,” most of the teams I've worked with first addressed the question: “where to start?”  That question applies to both implementation and improvements on the Scrum framew...

56 views 2 3
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you