Hi,
I create a Gantt and I create a task that its a milestone. I would like to show the milestones in the project manager dashboard.Do you know if its possible? I see the issue detail and i can't see any field that contains the information about this task is a milestone.
Thanks!!
Hi,
Currently milestones are stored only in an internal database. Very soon, however, they will be marked as a custom field/label on issues, and then setting up a dashboard will be a no-brainer.
Here's the ticket for this: https://softwareplant.com/jira/browse/GANTT-70