Send urgent Findings directly in the actual Sprint

Hi all,

We would like to have the findings created with Urgency "Sprint" or "Immediately" show automatically in the actual Sprint, when there is one active.

Atm they are displayed at the bottom of the Backlog (which is a long one) and don't draw attention to their urgency. Or maybe there is at least a way of showing them always at the top of the Backlog, without having to use the sorting in the main Filter, because then I loose the drag-and-drop functionality in the Backlog.

Thank you in advance for your support and ideas!

Loredana

1 answer

How about creating a swimlane based on "urgency"

Hi Christian,

What I mean is that when I create an urgent Finding, that it is automatically assigned to the present Sprint, as crazy as that sounds, not quite a Scrum like method.

The Swimmlanes are ok for viewing the Sprint Issues in Work-Mode, but we want to spare the work of pulling these urgent Defects manually into the Sprint, they should go in that Sprint automatically when they have a high Urgency.

Oh I see, I don't know if that's possible, not with GH as it is. I was referring to the "...way of showing them always at the top of the Backlog" part of your question :-)

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted 12 hours ago in United States

Atlassian acquires AgileCraft

         Good Day, Bad bad traffic, not sure why!!!! 1/2 hour commute took me 2 hours today 🤯 What helped me is that I kept browsing LinkedIn until...

46 views 4 0
View post

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you