Portfolio version 2, plan does not show completed stories Edited

I am trying to look at the progress at Epic and intiative level,  But when I creata a plan , it does not show stories that are completed thus prrogress bar shows 0 progress.  

Anyone could help, perhaps I ma configuring something wrong

 

1 answer

0 votes

Hi @Reza Montazeri,

 

There is a filter allowing you to decide how far to go look for completed items. For this, have a look at the "More" dropdown in the plan filter bar and select the "Completion Date" filter. You should then be able to specify the desired range.

If you are working with hours instead of story points, the progress is based out of logged hours which you might or might not use.

 

Cheers,

Thomas

Suggest an answer

Log in or Sign up to answer
Community showcase
Published 14 hours ago in Agile

How Scrum works? It starts with training and education

To answer “How scrum works,” most of the teams I've worked with first addressed the question: “where to start?”  That question applies to both implementation and improvements on the Scrum framew...

97 views 3 3
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you