JIRA service stopped after memory increase

Hi,

after increasing allocated memory for JIRA service where the -Xms was set to 256 (before 128) and the -Xmx to 1024 (before 512) (as described here http://confluence.atlassian.com/display/JIRA/Increasing+JIRA+Memory), the service stopped just few moments after i started it. I only managed to get to the log screen, but that was it, the service was down without any ERRORs logging. Has anyone else encountered this problem? Any clues where to look for the cause? The JIRA version is 4.4.3 the OS is windows 2003 R2 Enterprise x64 SP2

Thanks,

Rad

2 answers

1 accepted

0 votes
Accepted answer

what partially helped to solve this problem was to increase the size of a page file. Howewer, we only managed to increase the maximum memory pool, not the initial.

Check windows event viewer and jira log files.

Suggest an answer

Log in or Sign up to answer
Community showcase

Scrum Roles Explained: the Do's and the Don'ts

Hello Community,  Today we are going to talk about the three Scrum Roles. There is the Development Team, the Scrum Master and the Product Owner. In my opinion these three are all really impo...

156 views 2 6
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you