Is there any way to keep an item from being added to a Sprint before the Story Point field is filled in?

I'd like to enforce that stories do not get added to sprints before the estimation is filled in to make sure that the item has been looked at by developers before it gets added to the sprint.

2 answers

This widget could not be displayed.
Ahmad Danial Atlassian Team Oct 06, 2013

Hey there, Chris.

One of the options that I can think of is to add the Story Points to the Default Screen and make it mandatory in the Field Configuration. However, the only downside to this is that the moment the issue must have the Story Points the moment it is created. Let me know your thoughts about this.

This widget could not be displayed.

Not a great solution, it would be nice if this was something you could configure in JIRA Agile.

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Wednesday in Teamwork

What teamwork quotes inspire you?

Hey everyone! My name is Natalie and I'm an editor of the Atlassian Blog and I've got a question for you: What's your favorite quote about teamwork?  We've compiled a list here, along with...

176 views 18 7
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you