Is there any way to keep an item from being added to a Sprint before the Story Point field is filled in?

I'd like to enforce that stories do not get added to sprints before the estimation is filled in to make sure that the item has been looked at by developers before it gets added to the sprint.

2 answers

0 votes
Ahmad Danial Atlassian Team Oct 06, 2013

Hey there, Chris.

One of the options that I can think of is to add the Story Points to the Default Screen and make it mandatory in the Field Configuration. However, the only downside to this is that the moment the issue must have the Story Points the moment it is created. Let me know your thoughts about this.

Not a great solution, it would be nice if this was something you could configure in JIRA Agile.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published yesterday in Statuspage

194 years of downtime: looking back on incident data from 2018

Statuspage customers logged more than 194 years of collective incidents in 2018. That’s a whopping 87% increase from the  104 years logged in 2017 , and we aren’t even through December yet....

56 views 1 5
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you