Is there a way to view estimated hours and remaining hours for tasks from the scrum board?

I have been trying to see how I could configure the scrum board to view the original estimated hours and remaining hours for a task from the scrum board? I find it cumbersome to have to have to open up a specific task to view the hours.

4 answers

1 accepted

This widget could not be displayed.

I actually found the solution to my own question. I went into the configure option for my rapid board and changed to record estimated hours and remaining time versus story points and they all appeared! Wonderful.

This widget could not be displayed.

Yes, you can do that. Follow these steps.

1. Go into your scrum board,

2. select the view as list,

3. Click on configuration, click on tab card style

4. At the bottom, under the list tab add the fields original estimate and remaining.

Rahul

I was referring to the new board. It is the only way I can view multiple projects for a sprint. The classic board does not allow me to view by sprint based on our project setup since it only allows you to filter by component and versions.

This widget could not be displayed.

Are you referring to Classic Boards or the new boards?

This widget could not be displayed.

The new board.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Thursday in United States

Local Atlassian Research Workshop opportunity on Sep. 28th

We're looking for participants for another workshop at Atlassian! We need Jira admins who have interesting custom workflows, issue views, or boards. Think you have a story to sh...

44 views 0 0
View post

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you