Is there a way of adding in an additional layer above subtasks?

Hi, the way we have our Jira layed out is the top level is our Main Projects - then we have our Key Initiatives and then under that we have sub tasks. Is there a way of creating another 'layer' between the main Issue and then the sub task?

1 answer

1 accepted

Accepted Answer
2 votes

Not without plugins - the heirarchy in Jira is category - project - issue - subtask. That's it.

With Greenhopper, you might be able to make use of the Epic functionality, but that lives above "issue".

There are some other plugins which do some related stuff, but I think your best bet is the "structure" plugin - https://marketplace.atlassian.com/plugins/com.almworks.jira.structure

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Featured Groups

Tuesday tips & tricks: What is the Atlassian Community?

It's officially Tuesday, which means it's officially time for another tip to help you better navigate this space we call the Atlassian Community. 😄 I got a great question from community member, Sa...

122 views 6 8
View post

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you