Hi, the way we have our Jira layed out is the top level is our Main Projects - then we have our Key Initiatives and then under that we have sub tasks. Is there a way of creating another 'layer' between the main Issue and then the sub task?

1 answer

1 accepted

2 votes
Answer accepted
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 25, 2013

Not without plugins - the heirarchy in Jira is category - project - issue - subtask. That's it.

With Greenhopper, you might be able to make use of the Epic functionality, but that lives above "issue".

There are some other plugins which do some related stuff, but I think your best bet is the "structure" plugin - https://marketplace.atlassian.com/plugins/com.almworks.jira.structure