I am having only issue type=tasks in my sprint and now i am not shown burndown chart

I am having only issue type=tasks in my sprint and now i am not shown burndown chart

I am using JIRA cloud.

Is it bacause i do not have any story in my sprint ? or this is configuration issue?

2 answers

This widget could not be displayed.

Hi Tahira,

Boards default to using Story Points as their estimation statistic.  It is likely that your tasks are using some other estimation unit (e.g. man hours?) which means they do not burndown any story points.

 

However, you can re-configure your board to use your tasks' estimate field by going to:

Board/Configure

'Estimation' Tab

Choose appropriate value in 'Estimation Statistic' field

This widget could not be displayed.

Hi Tony,

Thanks for help, I do not mentioned in man hours, I story pointed my task like storypoint =4 to each and there were 11 tasks there.

May be this is configuration issue. 

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Wednesday in Teamwork

What teamwork quotes inspire you?

Hey everyone! My name is Natalie and I'm an editor of the Atlassian Blog and I've got a question for you: What's your favorite quote about teamwork?  We've compiled a list here, along with...

151 views 16 7
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you