I am having only issue type=tasks in my sprint and now i am not shown burndown chart

I am having only issue type=tasks in my sprint and now i am not shown burndown chart

I am using JIRA cloud.

Is it bacause i do not have any story in my sprint ? or this is configuration issue?

2 answers

Hi Tahira,

Boards default to using Story Points as their estimation statistic.  It is likely that your tasks are using some other estimation unit (e.g. man hours?) which means they do not burndown any story points.

 

However, you can re-configure your board to use your tasks' estimate field by going to:

Board/Configure

'Estimation' Tab

Choose appropriate value in 'Estimation Statistic' field

Hi Tony,

Thanks for help, I do not mentioned in man hours, I story pointed my task like storypoint =4 to each and there were 11 tasks there.

May be this is configuration issue. 

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Asked 12 hours ago in Confluence

What are the resources that you use to learn more about Atlassian Products?

I am gathering information about resources available for Atlassian product knowledge transferring for a presentation in our local Atlassian User Group. I want to group them in four categories From ...

59 views 3 4
View question

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you