I am having only issue type=tasks in my sprint and now i am not shown burndown chart

I am having only issue type=tasks in my sprint and now i am not shown burndown chart

I am using JIRA cloud.

Is it bacause i do not have any story in my sprint ? or this is configuration issue?

2 answers

Hi Tahira,

Boards default to using Story Points as their estimation statistic.  It is likely that your tasks are using some other estimation unit (e.g. man hours?) which means they do not burndown any story points.

 

However, you can re-configure your board to use your tasks' estimate field by going to:

Board/Configure

'Estimation' Tab

Choose appropriate value in 'Estimation Statistic' field

Hi Tony,

Thanks for help, I do not mentioned in man hours, I story pointed my task like storypoint =4 to each and there were 11 tasks there.

May be this is configuration issue. 

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Featured Groups

Tuesday tips & tricks: What is the Atlassian Community?

It's officially Tuesday, which means it's officially time for another tip to help you better navigate this space we call the Atlassian Community. 😄 I got a great question from community member, Sa...

53 views 2 4
View post

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you