How to write a JQL to know when the status was changed?

Mozart Alves June 16, 2017

I want to create a report showing when my issues were started and finished. But someone was created as backlog and other one started as In Progress.

 

1 answer

0 votes
Fabio Racobaldo _Herzum_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 23, 2024

Hi @Mozart Alves ,

unfortunately you can't do that through a JQL. That information is stored in the issue history.

Fabio

Suggest an answer