We've recently upgraded to JIRA v 7.3.2 and could see team velocity in the velocity chart. However, my executive VP is asking to get the average velocity of 15 teams that can be useful for future predictability. Also looked at the control charts but those are based on "days" but not "story-points" so looking for simple ways to know the average velocity (in story-points) for the future predictability stand point.
Hi BigD,
Out of the box you will not be able to measure this. However, with plugins such as eazybi this is possible: https://community.eazybi.com/t/average-velocity-for-multiple-projects/4199
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.