How can i move tasks from "to do" to "inprogress" in my rapid board

How can i move tasks from "to do" to "inprogress" in my rapid board by drugging?

I am trying to do so but can only move it to "done"...

thanks!

2 answers

1 accepted

Accepted Answer
1 vote

Do you have permission to do so in the workflows? Normally "assignee" can only move a ticket to "In Progress" but that is defined in the workflow conditions.

It could be one of the following 'simple' reasons...

1. Your workflow doesn't have a transition step for To-Do to In-Progress

2. The Jira project you are using with Greenhopper is not using the workflow above (Administrator | Your Project | Workflows)

3. The issue type you are trying to move to In-progress is not configured to use the workflow above (Administrator | Your Project | Workflows)

4. Your Rapid Board columns are not mapped to the statuses defined for In-progress in the workflow above (Agile | Rapid Board | Configure | Columns)

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted 3 hours ago in Canada

TOPIC TUESDAY - Oct 16th - Fav Atlassian Logo

Hey folks, We are back with your Topic Tuesday Question for the week. This week we are asking what is your fav new Atlassian logo? My vote would be for Statuspage. Let us know your thoughts! &nbs...

15 views 2 0
View post

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you