How can I drop non-working days from the burndown chart?

George Carvill
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 5, 2013

I have defined our time as five days a week, eight hours a day.

The (Greenhopper) chart still shows weekend days. Even when I uncheck "Show Non-Working Days"

1 answer

1 accepted

0 votes
Answer accepted
George Carvill
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 5, 2013

Figured it out. I was looking for a global setting. Instead the setting is for each Sprint board.