Greenhopper priorities vs ranking

What role do issue priorities have when your project is managed by Agile Scrum, where priorities are ordered by rank, instead of issue priority?

2 answers

1 accepted

This widget could not be displayed.
Yew Teck En Atlassian Team Feb 24, 2013

Ranking allow you to emphasize more on a group of issues rather than based on the general issue priorities.

For example, you may have 5 issues that having the same issue priority. However, there are one or two issues that having higher priority than the rest which you would want to use the ranking to rank it higher as priority.

This widget could not be displayed.

You can further group issues by priority. That way you can use the priority to define swimlanes for example...

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Wednesday in Teamwork

What teamwork quotes inspire you?

Hey everyone! My name is Natalie and I'm an editor of the Atlassian Blog and I've got a question for you: What's your favorite quote about teamwork?  We've compiled a list here, along with...

178 views 18 7
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you