Editing a Version Start Date

Jeff Wojnar September 4, 2012

Once a version is created with an end date and no start date, can a start date be added?

2 answers

0 votes
pkirkeby
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 20, 2012

See this page for editing a start date after adding a version:

https://confluence.atlassian.com/display/GH056/Adding+a+Version

Specifically the part where it says:

"You can edit the Start date and End date later if you need to, via the 'Statistics' column of the Planning Board."

Cheers,

Pelle

0 votes
SimonS
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 4, 2012

Hi Jeff,

Versions in JIRA don't have a start date - only a "Release Date". Start dates cannot be added. What were you hoping to get out of adding a start date to a version? There may be another way to get what you are after.

-Simon