Configuration of "Original Estimate" field as required

I would like to get required Original Estimate field in Open->In_Progres transition. User should not be able to Start progress task until Original Estimate field is populated.

How can I configure it it (I am not able to find any Original Estimate field configuration) ?

Regards,

Bartek

1 answer

Its called "Time Tracking".

I agree, its weird and not intuitive.

You can add a description to it to help your Eng understand that logged work goes against that field.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published yesterday in Jira Ops

Jira Ops Early Access Program Update #1: Announcing our next feature and a new integration

Thanks for signing up for Jira Ops! I’m Matt Ryall, leader for the Jira Ops product team at Atlassian. Since this is a brand new product, we’ll be delivering improvements quickly and sharing updates...

267 views 0 6
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you