Can Sprint Start & End dates be added for the Sprint Pipeline (beyond current sprint)

Hi forum!

We have a large part of our backlog estimated, and so I'd like to organise the backlog into sprints depending on my team's availability over the coming weeks - up to say the next 3 or 4 sprints in advance.

Its just to get a rough idea of when items might be delivered, although the team only commits to items in the backlog at sprint planning before the sprint starts.

But I can't see a way to enter any provisional start or end dates for the future sprint markers.

I suppose it would be odd to record dates beyond the current sprint because the team hasn't committed to those future sprints, but I'm just looking to record a rough future pipeline of work.

Any ideas on how I could acheive that?

Thanks!

2 answers

1 accepted

Accepted Answer
0 votes

I voted for an existing feature request:

https://jira.atlassian.com/browse/GHS-6231

I suggest that you add this information to a new feature request on https://jira.atlassian.com

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Featured Groups

Tuesday tips & tricks: What is the Atlassian Community?

It's officially Tuesday, which means it's officially time for another tip to help you better navigate this space we call the Atlassian Community. 😄 I got a great question from community member, Sa...

66 views 2 6
View post

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you