Can I create 2 sprints that run concurrently?

We have 2 scrum teams that will be running staggered sprints. For example, Team 1 Sprint Planning will happen today and Team 2 Sprint Planning will happen one week from today. I do not see a way to create a second sprint without first closing the initial sprint.

Any help is appreciated.

2 answers

1 accepted

0 vote

Hi Robert,

The latest version of Greenhopper allows you to have multiple active sprints running in parallel. This version is not available for OnDemand instances yet, but it should be released shortly. Please see Greenhopper 6.0.3 Release Notes for more details about it.

Cheers,

Clarissa.

To all still interested: the feature is already available in OnDemand GreenHopper, if you activate it under JIRA Admin > GreenHopper Labs.

Hello! Does this feature work in the downloaded version of Jira Agile v6.3.1?

Thanks - Janet

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Thursday in Marketplace Apps

Tips on how to choose the best estimation method for your planning

Planning and grooming sessions all come with their own sets of rules. Team members meet to estimate stories or other work items, all according to an agreed-upon process. And with every session comes ...

71 views 0 11
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you