Can I configure Versions to ignore Story Point estimates on Epics?

Our board is configured to use story point estimation, and with this in place, the Version progress panel appears to sum up the story point estimates of all related issues. Is there any way to configure the version progress panel so that it ignores Story Point Estimates on Epics? (Or should I just add a custom field to hold my Epic level Estimate?)

1 answer

1 accepted

This widget could not be displayed.

I ran into the same problem.  I think your Epic Story Point field is a reasonable workaround.

One other option is to define a filter that returns 'stories from fully decomposed epics AND epics that are not fully decomposed'  (We have custom workflow states to make the JQL easier)

You can then configure an extra agile board based on this filter and its version & release reports will avoid the double accounting

 

 

 

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted 7 hours ago in New to Jira

Are you planning to trial, or are currently trialling Jira Software? - We want to talk to you!

Hello! I'm Rayen, a product manager at Atlassian. My team and I are working hard to improve the trial experience for Jira Software Cloud. We are interested in   talking to 20 people planning t...

13 views 0 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you