Burndown chart in Greenhopper, no redline showing progress

In my previous sprints there's a redline showing progress. There's no redline in my current sprint? What do I check to get this back?

1 answer

1 accepted

When did your sprint start? The red line shows up from the start of the sprint to the current date, if you have only just started the sprint you might not see it.

Also, it could be if you don't have any issues in your sprint with estimates, you might not see a red line, but in that case you wouldn't see a grey guideline either. You can check by viewing the Sprint Report the total estimates for completed and incompleted issues so far.

Thank you! I messed up and started the sprint in the future.

Suggest an answer

Log in or Join to answer
Community showcase
Jason Wong
Published yesterday in Agility Beta

Welcome to agility

Every team in the world is unique, and so   Atlassian believes   that each and every team's best way of working  needs to  be molded to their unique circumstances  – ...

278 views 6 15
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot