Assign done stories to epics

We've just migrated from Redmine to JIRA/Greenhopper and are facing the issue that it simply isn't possible by no means to assign a done story to an epic as the stories won't appear in the backlog. Is that right?

Of course, the workaround would be to reopen stories, assign and close them afterwards but I still have the slight hope that there might be a smarter way.

1 answer

1 accepted

0 votes
Accepted answer

That is currently true. You cna vote for https://jira.atlassian.com/browse/GHS-6854 if you wish to see that change.

Also if you do re-open and close your issues I suggets using the bulk edit functionality, and add a unique label to the opened tickets "to-be-closed" that you can use in a follow up bulk edit to re-resolve everything.

Ok, I've voted for the issue. Thanks!

Suggest an answer

Log in or Sign up to answer
Community showcase

Scrum Roles Explained: the Do's and the Don'ts

Hello Community,  Today we are going to talk about the three Scrum Roles. There is the Development Team, the Scrum Master and the Product Owner. In my opinion these three are all really impo...

131 views 2 5
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you