Is there a way to find the story points that were added after sprint start

I am creating a report for which need  the story points that were added after sprint start

1 answer

@srinivas kolaparthi If you go to the Project then Reports and click on either the Burnup Chart or the Burndown Chart, under the graph there is a detailed list of all activities within the sprint.

Here, it will tell you any time the scope of the sprint is changed, caused either by estimated tasks that have been added to the sprint, or when an estimate of a task is changed.

Thanks for the response.

Can we access Burnup chart using restfulservices?

Regards

Srini

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Apps & Integrations

🍻🍂Apptoberfest Update: Upcoming Virtual Events 🎉

Hello Community! I hope you've been enjoying the 🍂Apptoberfestivities🍂 (I know I have!) The event is heating up next week with a series of virtual events that we're calling the 🍻🍂Partner App ...

107 views 1 8
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you