I am creating a report for which need the story points that were added after sprint start
@srinivas kolaparthi If you go to the Project then Reports and click on either the Burnup Chart or the Burndown Chart, under the graph there is a detailed list of all activities within the sprint.
Here, it will tell you any time the scope of the sprint is changed, caused either by estimated tasks that have been added to the sprint, or when an estimate of a task is changed.
Thanks for the response.
Can we access Burnup chart using restfulservices?
Regards
Srini
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If you already heard about Smart Commits in Bitbucket, know that you just stumbled upon something even better (and smarter!): Genius Commits by Better DevOps Automation for Jira Data Center (+ Server...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.