Working hours and days management in Portfolio

Hi,

What happens with the teams capacity if the same Public holiday is added both through the configuration of Development of Roadmap in "Working hours and days management" and through Teams absence management? Will the system recognize that this is the same day and ignore this, or will the hours be deducted twice?

1 answer

1 accepted

0 vote

Hi @Sigita Martinaityte,

 

Portfolio uses those data to define the team members availability, holidays which applies to all teams and members of a plan have precedence over absences and exceptions.

This means the capacity of the teams and team members during a holiday will be 0 and not any lower even if there are additional absences on that day.

 

Cheers,

Thomas

Thank you! This helps :)

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Josh Frank
Posted Apr 04, 2018 in Portfolio for Jira

Factom: Portfolio for Jira case study

Recently, as part of a   series of Portfolio for Jira case studies, we spoke with Carl DiClementi, Director of Product Management at   Factom   about how he uses Portfolio for Jira. In...

857 views 5 4
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you