Why is Portfolio displaying an "availability violation"

I've got a portfolio plan defined with teams that have the necessary skills and estimates.  Yet, the scheduler is displaying an "availability violation".  Has anyone else experienced this?  Have any thoughts on things I could try to resolve it? 

1 answer

1 accepted

I figured this issue out.  I had required skills split across teams. Portfolio won't allow multiple teams to be assigned at the story level.  Once I put all the people/skills in one team, the availability violation was resolved.

Now if I could just figure out why Portfolio thinks there are skill gaps to complete a story.

Hey Peter, have you found any way of finding where ths kill gaps are in a plan?

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Posted May 01, 2018 in Portfolio for Jira

New Portfolio for Jira Demo

We recently launched a brand new Portfolio for Jira demo where you can learn: The essentials for getting started with Portfolio for Jira How to create a realistic roadmap based on your work in Jir...

236 views 0 7
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you