Why is Portfolio displaying an "availability violation"

I've got a portfolio plan defined with teams that have the necessary skills and estimates.  Yet, the scheduler is displaying an "availability violation".  Has anyone else experienced this?  Have any thoughts on things I could try to resolve it? 

1 answer

1 accepted

I figured this issue out.  I had required skills split across teams. Portfolio won't allow multiple teams to be assigned at the story level.  Once I put all the people/skills in one team, the availability violation was resolved.

Now if I could just figure out why Portfolio thinks there are skill gaps to complete a story.

Hey Peter, have you found any way of finding where ths kill gaps are in a plan?

Suggest an answer

Log in or Join to answer
Community showcase
Josh Frank
Posted Dec 01, 2017 in Portfolio for Jira

Portfolio for Jira: Share your tips!

The Portfolio for Jira team wants to hear from you. Share your top tips for building a great Portfolio for Jira plan for a chance to win some Atlassian swag.  Do you structure your teams i...

542 views 6 8
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot