Also when creating a new plan and syncing with a JIRA project it uses the remaining estimate as the estimate when I would prefer to use the original any way to configure that?

4 answers

0 votes
Thibault May 24, 2017

Any update on this one? Thanks!

0 votes
Arvin Arora January 16, 2017

Any idea / update on this? This seems quite inconsistent as typically the original estimate should be used when creating a new issue!

0 votes
Todd Farrar December 6, 2016

Looking for an update as well - PF 2.0 is only updating the Remaining Estimate field in JIRA when committing changes. 

0 votes
Dustin Foreman October 28, 2016

Has there been an update on this?