What is the number in parentheses in the timeline Story grouping by team

In Portfolio, in the timeline, if you select group by team, after the team name there is a number in parentheses.  For instance in the attachment what is "(49)"?  What is that? number in parentheses.jpg

1 answer

1 accepted

2 votes
Cristiano Oliveira Community Champion Nov 22, 2017

Hi Joel!

It looks to me this is the number of issues in which this team will work.

In your example, this team will work in 49 stories.

Thanks,

Cristiano

Hi Cristiano,

Thanks! Looks like you are right.  It seems to be a total of all issues whether they are estimated or not.  Since the timeline shows only estimated issues beyond the current sprint,  it will typically show fewer issue 

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Posted Jun 26, 2018 in Portfolio for Jira

New Portfolio for Jira Getting Started Guide

We've just launched a brand new guide to help you get started with Portfolio for Jira.  This guide is a companion piece to our new demo. The guide walks you through use-cases, best practices an...

254 views 7 4
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you