What is the number in parentheses in the timeline Story grouping by team

Joel Feldman November 22, 2017

In Portfolio, in the timeline, if you select group by team, after the team name there is a number in parentheses.  For instance in the attachment what is "(49)"?  What is that? number in parentheses.jpg

1 answer

1 accepted

2 votes
Answer accepted
Cristiano Mariano
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 22, 2017

Hi Joel!

It looks to me this is the number of issues in which this team will work.

In your example, this team will work in 49 stories.

Thanks,

Cristiano

Joel Feldman November 27, 2017

Hi Cristiano,

Thanks! Looks like you are right.  It seems to be a total of all issues whether they are estimated or not.  Since the timeline shows only estimated issues beyond the current sprint,  it will typically show fewer issue 