Story points disabled in portfolio

In Portfolio,  I want to use story points for planning mode.   However on the Configure->Scheduling page the story points option button is disabled,  and I cannot select.    I cannot find out why this is.

Please help,  as only way for me to use Portfolio is if I can set it up to use story points

1 answer

3 votes

Hi Linda - this option gets disabled when you have a team set to Kanban, as for story point scheduling currently Portfolio requires the notion of a sprint and velocity. if you switch your teams to "Scrum", you should be able to switch to story points too. If your teams do Kanban but still estimate in story points, you could simply configure them to use "Scrum" with 1 week iteration length, and plan weekly. 

Hi, I had the same experience (could not use story points).  I had changed an existing plan to use a different board.  I could not use story points.  But when I deleted that plan, and made a new one, then I could use story points.  Is this normal?

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Posted Jun 26, 2018 in Portfolio for Jira

New Portfolio for Jira Getting Started Guide

We've just launched a brand new guide to help you get started with Portfolio for Jira.  This guide is a companion piece to our new demo. The guide walks you through use-cases, best practices an...

246 views 7 4
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you