Portfolio indicates there's 1 Uncommitted Change, but there's not

Not entirely sure how/when this happened to my Portfolio plan, but I believe it occurred after adjusting some of my Team Members. After changing some people around (deleted one, changed available hours of another), I ended up with the following condition:

My Plan shows 1 Uncommitted change, even though when I go to commit it, there is nothing changed and and I get the smiley face that I'm all set.

The other condition is now I get the warning that my Plan has exceeded the 5 Year Horizon. When, actually, I don't believe there is anything actually driving it. Maybe there's one story that has some weirdness that's causing this, but I haven't found it yet.

Anyone ever experienced this?

Terrell

 

1 answer

1 accepted

0 vote

Hi @Terrell Teague,

 

For this uncommitted changes: this is a known issue, I'd suggest having a look at https://jira.atlassian.com/browse/JPOSERVER-1527 for status tracking and workarounds.

 

For the schedule hitting the planning horizon: Have a look at the estimated issues and look for an error sign in the scope table, being able to identify which issue is causing this is a good first step. The typical situation is that due to skills or just availabilities work can be started but not finished which pushes Portfolio to look further in the future until hitting the planning horizon.

Hopefully that will help.

 

Cheers,

Thomas

The fix you mentioned for the uncommitted change did the trick, thanks!

Was eventually able to find the story that was causing my schedule to blow up thanks to your input.

Terrell

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Josh Frank
Posted Apr 04, 2018 in Portfolio for Jira

Factom: Portfolio for Jira case study

Recently, as part of a   series of Portfolio for Jira case studies, we spoke with Carl DiClementi, Director of Product Management at   Factom   about how he uses Portfolio for Jira. In...

269 views 5 4
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you