Overlapping Active Sprints

I'm getting an error from Portfolio that I have multiple overlapping sprints, but when I look at the sprints, they are not actually overlapping. Is this a new bug or something I'm missing?Screen Shot 2018-01-02 at 4.37.30 PM.pngScreen Shot 2018-01-02 at 4.37.49 PM.pngScreen Shot 2018-01-02 at 4.38.05 PM.png

1 answer

1 accepted

1 vote

Hi @Dominic O'Connor,

 

The most likely issue is that your sprint DEMETER-RS-26 is in the past but is still active (not closed) saying that it is still running. As a result it is in fact overlapping EOS-RS-1.

If that makes sense, I'd advise to complete the DEMETER-RS-26 sprint and then reload / recalculate the plan to see if the error persists.

 

Cheers,

Thomas.

Yeah that seemed to do it. Overlapping was confusing nomenclature since the end date that we defined didn't actually overlap with the next sprint, but conceptually your explanation makes sense. Thanks!

Suggest an answer

Log in or Join to answer
Community showcase
Josh Frank
Posted Dec 01, 2017 in Portfolio for Jira

Portfolio for Jira: Share your tips!

The Portfolio for Jira team wants to hear from you. Share your top tips for building a great Portfolio for Jira plan for a chance to win some Atlassian swag.  Do you structure your teams i...

564 views 6 8
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot