Multiple version of a product to plan

Hi, we are newly using the Portfolio and we are on our way to implement it product by product & team by team. And we have a decision to take on how to implement the plan for multiple version work when done by a single team.

Let me explain we have the product team A which is working on the product Z, which has 3 maintained version A1, A2 and A3 and a future new version A4. So far, in their backlog, specific for product Z, each version exists as 'versions' and the backblog of issues are assigned to each fix version and grouped in sprint dedicated to a single version and to each time a specific lengh. So this means for instance :

Sprint 11 - version A1 for 2 weeks for team A

Sprint 12 - version A2 for 1 week for some members of team A

Sprint 13 - version A3 for 3 weeks  for team A

Sprint 14 - version A4 for 4 weeks  for team A

Sprint 15 - version A1 for 1 week for some members of team A

... 

But, in the Portfolio, the most important plan we want to follow and manage carrefully is the version A4 since it's where new features are. The 3 other versions are maintenance version and we do the max per sprint to solve all the bugs. I'm not sure yet, we'll get all those bugs in the Portfolio plan.

Now that we'll be using the Jira Portfolio module, I was wondering what would be the most ideal way to manage those sprint & versions.  At the moment, I do have the version A4 scope in the plan and I'm getting the teams. But once we'll get to the estimates and planning, I know that I'll face an issue, since the plan won't be continuous (interruption with the maintenance sprints), so I wanted to brainstorm this here with those that might either have some experience or idea how to best manage this.

 

Regards.

1 answer

Has anyone any idea for this question ?

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Posted May 01, 2018 in Portfolio for Jira

New Portfolio for Jira Demo

We recently launched a brand new Portfolio for Jira demo where you can learn: The essentials for getting started with Portfolio for Jira How to create a realistic roadmap based on your work in Jir...

236 views 0 7
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you