Jira Portfolio: How do I account for unknown stories that will be created

So when a project kicks off we know that we dont know all the stories, how does Jira porfolio account for that? we are just about to start using it but I dont know how I will be able to estimate end date from the start as it will not be correct.

1 answer

0 vote
Cristiano Oliveira Community Champion Nov 22, 2017

Hi Tom! How are you doing?

In case you have any high level estimative, you would put them on the Initiative or Epic level and, after creating the stories, refine this estimative.

As your project goes on and you have more details, your plan will get more accurate.

Hope this helps!

Cristiano

Suggest an answer

Log in or Join to answer
Community showcase
Josh Frank
Posted Dec 01, 2017 in Portfolio for Jira

Portfolio for Jira: Share your tips!

The Portfolio for Jira team wants to hear from you. Share your top tips for building a great Portfolio for Jira plan for a chance to win some Atlassian swag.  Do you structure your teams i...

568 views 6 8
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot