Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

If estimate of Portfolio Plan has mapping with remaining estimate of linked issue, why do changing estimate value on plan updates remaining as well as original estimates of linked issue with estimates from Plan.

Radha Khullar June 4, 2015

.

1 answer

0 votes
Martin Suntinger
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
June 9, 2015

The assumption is: As long as no plan updates have been made and there is no value for "Originally planned" set in JIRA Portfolio (you can see this column only when using the "Show completed issues" toggle), then we have a case of doing the initial planning, in which we're rather working with the initial (original) estimates, and what is remaining to be scheduled will be the same value, thus both of them are set to the same value on sync.

Once you've done a plan update, and the previous estimates are stored as "Originally planned", the sync with update only the remaining estimate field on the JIRA issues, and the value in the "orignally planned" column is synced to the original estimate. 

In short: We assume during initial planning, we're rather estimating the original values, and original=remaining, later when updating, only the remaining is synced. 

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events