How to consider the velocity of the past sprints in Portfolio

JörgS June 16, 2017

Using Portfolio Cloud

I would like Portfolio to calculate the Issues in a sprint based on the velocity of the team. 

Currently I can see the capacity and if the sprints are overbooked. I can also see in the Board in the Velocity Chart, that the team commitment is higher than the result.

I would like to see a realistic timeline where issues assigned to a sprint based on the capacity and velocity.

Is this supported by Portfolio?

 

Thanks,

Joerg

1 answer

0 votes
Deleted user June 27, 2017

Sort of.  Try going into the Teams view and click on the number representing Velocity (pts) on the right side.  In the popup that appears, click the Past Velocity tab and then click the Use suggested velocity button.

Not sure if it's exactly what you're looking for but it's the closest I can think of.

JörgS July 4, 2017

Hi Steven,

yes, that is exactly what I'm looking for. Unfortunately there is no popup. I worked in a Server environment and I got this popup but in Cloud not. Is there a different functionality?