How do i import closed story to portfolio?

I am trying to import projects into portfolio and need to include closed issues so that we can show progress made thus far prior to using portfolio. I can't seem to get closed stories to show up in the import screen whether i'm importing from a project or filter. the filters do not filter based on status so when searching for filter i can see closed stories, but not in portfolio. please help.

1 answer

0 votes

Hi @Vivian Lin,

As Portfolio for JIRA is a forward planning tool, the default filtering inside a plan is set to filter done issues that are older than the current sprint. You can see these filters (and their default settings) under the more button in the filter menu. 

Have a look to see if changing those filters helps you. 

This page here, will detail the other filters that exist inside of Portfolio. 
https://confluence.atlassian.com/jiraportfoliocloud/using-scope-filters-828785257.html

Cheers,
Allard

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,371 views 15 19
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you