I'm currently planning Epics in Portfolio.
We've estimated an epic to take 15 days
When Portfolio automatically schedules it sets the start / end date to be Nov 8/ Nov 19.
I expected the scheduler to slot 3 weeks of time. Nov 8 -> Nov 29 (as it doesn't include weekends)
I believe that it's assigning 11 days because it's assignign two people to work on it. How can I set it up so that automatically, only one person is assigned to an epic?
Hi @Vincent Huang,
This is currently not supported, I've created a feature suggestion here: https://jira.atlassian.com/browse/JPOSERVER-2034
I'd encourage you to vote and explain your use case on it in the comments!
As a workaround, you would currently have to manually assign the epic to a single team member.
Cheers,
The Portfolio for Jira Team
This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.
Read moreRecently, as part of a series of Portfolio for Jira case studies, we spoke with Carl DiClementi, Director of Product Management at Factom about how he uses Portfolio for Jira. In...
Connect with like-minded Atlassian users at free events near you!
Find a groupConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no AUG chapters near you at the moment.
Start an AUGYou're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.