How do I configure so that only one person is assigned to a epic?

I'm currently planning Epics in Portfolio. 

We've estimated an epic to take 15 days

When Portfolio automatically schedules it sets the start / end date to be Nov 8/ Nov 19.

 

I expected the scheduler to slot 3 weeks of time. Nov 8 -> Nov 29 (as it doesn't include weekends)

I believe that it's assigning 11 days because it's assignign two people to work on it. How can I set it up so that automatically, only one person is assigned to an epic?

1 answer

1 accepted

This widget could not be displayed.

Hi @Vincent Huang,

This is currently not supported, I've created a feature suggestion here: https://jira.atlassian.com/browse/JPOSERVER-2034

I'd encourage you to vote and explain your use case on it in the comments!

As a workaround, you would currently have to manually assign the epic to a single team member.

Cheers,

The Portfolio for Jira Team

Suggest an answer

Log in or Sign up to answer
Community showcase
Asked Jun 26, 2018 in Portfolio for Jira

New Portfolio for Jira Getting Started Guide

We've just launched a brand new guide to help you get started with Portfolio for Jira.  This guide is a companion piece to our new demo. The guide walks you through use-cases, best practices an...

797 views 7 5
View question

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you