How could I see the target dates from Portfolio in JIRA?

I need to know a way for adding the target (start and end) date fields of Portfolio in the JIRA issues themselves.

A manager will update those dates in Portfolio but each asignee need to see the start and end dates in the issue page.

2 answers

Hi Carlos,

Unfortunately you can't surface Target start and end fields in the JIRA issue screens. These fields are mostly intended to assist Portfolio users in roughly estimate and baseline the work on an issue inside Portfolio.

You can always create a suggestion in https://jira.atlassian.com and the team will consider if and when this suggestion will be prioritized.

I hope this helps,

~ edit

Since version 2.9 you can surface the target start & end dates within Jira. Read more here: https://confluence.atlassian.com/jiraportfolioserver/showing-portfolio-custom-fields-in-jira-857058481.html

Hi Roi, thank you very much for the info. Is there a way for commiting the asignee field of Portfolio in JIRA issues?

Kind regards.

Hi Carlos,

In Portfolio there is no assignee field but a "member" field. You can add it to your scope table to view it and assign a member to a task or let Portfolio automatically assign it.

The default issue level to be assigned by Portfolio is sub-task. If you wish Portfolio to assign higher level hierarchy items such as stories to a team member you can adjust it in the configure page under scheduling options.

Hope that helps,

~ edit

In Portfolio for Jira new experience the assignee field is available to view and edit. 

Thanks for the info Roi

Hello @Roi Fine,

 

Thank you for the explanation. I have another question and some assistance required, related to the Target start and Target end fields.

 

I saw that these fields return a NULL value in the JIRA MySQL DB, even when there is a date value entered in the field/s.

 

Is there any way where we can find the values of these fields?

 

Regards,
Rahul Savaikar

Roi Fine Atlassian Team Jan 02, 2019

Hi @Rahul Savaikar,

 

The target start/end values are stored in the entity_property database table. It is a different table where other Jira custom fields values are stored.

Please let me know if that helps,

 

Best,

 

Like 1 person likes this

Good morning @Roi Fine,

 

Firstly, wish you all a very happy, healthy and a successful new year ahead!

 

And, yes, your answered resolved my issue :) - thank you very much.

 

Have a good one!

 

Best Regards,

Rahul Savaikar

0 votes
Yann I'm New Here Jan 04, 2019

Hi there,

 

In used the Import Bulk Issue and set the Start Date, but when i look in Portfolio , it can't mapped with Target Start.

 

1.png

 

Do you have any solution?

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Jan 15, 2019 in Statuspage

Introducing Statuspage Getting Started guides! First up: What is Statuspage?

Over the next several weeks we'll be sharing some of our Getting Started guides here in the community. Throughout this series of posts, we'd love to hear from customers and non-customers ab...

270 views 4 2
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you