Due Date vs. Target End Date

Helmut Schreiber February 8, 2020

The Due Date is used by us as Feature Complete Date. The Target End Date is the time at which a feature is deployed.


This now triggers a warning in the Portfolio Plan, because the Due Date must not be before the Target End Date.

Now it is different from company to company how the dates are used and what they mean. Especially if there are Kanban and Scrum teams at the same time

According to our company rules, a due date can therefore be before the Target End Date. So where can I configure the warnings in Portfolio?

1 answer

0 votes
Brant Schroeder
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 25, 2021

@Helmut Schreiber Target dates are a delivered feature in portfolio that are used for planning and to show when work is expected to begin and end.  These are not a hard deadline like a due date.  Sounds like you just need to change the usage of the fields to align with the software.  There is no way to change the warnings.