Automatically Set Due Date

Im just getting set up with Jira and Portfolio after moving away from Asana. We have been used to setting due dates for when work should be completed, and while I know that due dates can be set in an issue view, how can I go about setting up due dates for issues based on the schedule created in Portfolio. Ideally, I would get a schedule for a based on capacity, make adjustments for priorities, and then when the updates are committed, the due dates would be set for items inside of the Jira issues. 

2 answers

This widget could not be displayed.
Claudio Ombrella Community Champion Jan 24, 2018

I am not sure if I will be able to help here, but it is my impression that you need to enter a due date in order to do your planning - in a few words it is the other way around.

This widget could not be displayed.

Hi @George Birnbaum,

I would suggest using the Target start and Target end date fields provided by Portfolio for this. (Docs for Server and Cloud).

 

Cheers,

Thomas

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Jun 26, 2018 in Portfolio for Jira

New Portfolio for Jira Getting Started Guide

We've just launched a brand new guide to help you get started with Portfolio for Jira.  This guide is a companion piece to our new demo. The guide walks you through use-cases, best practices an...

631 views 7 4
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you