Automatic Scheduling calculates a very inefficient plan

I'm setting up my first plan, but it seems like the auto scheduling does not work. 

One of the times I recalculated the plan and it looked right be next time it started to look wrong again.

Help me find the problem:

I have a story that will not be started today but is planned a week ahead and this is not right if I look at the cal rules behind.

1. it is the highest in priority

2. it has no blocking issues

3. the person assigned has no other issues 

4. it is the critical largest issue in the plan

what have I done wrong?

1 answer

Hi Anders,
You might find the following links useful to learn how to use Portfolio.

Cheers,

Hi Maria,

I have read all the documentation carfully, but do not find answers to this question.

We are considering investing in the tooling, but if this core functionality cannot work, it is probably not going to happen.

Any possibilities for getting support for this issue ?

Suggest an answer

Log in or Join to answer
Community showcase
Josh Frank
Posted Dec 01, 2017 in Portfolio for Jira

Portfolio for Jira: Share your tips!

The Portfolio for Jira team wants to hear from you. Share your top tips for building a great Portfolio for Jira plan for a chance to win some Atlassian swag.  Do you structure your teams i...

537 views 6 8
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot