Adding boards in Portfolio scenario

I want to add an additional board/project in Scenario b of my portfolio planning. How can I do that? Reason: I want to separate specific projekt workload from Feature requests and want to show the impact of feature Requests

Thanks in advance

1 answer

This is not possible - Scenarios are fixed to the plan as you have it configured to boards/projects.

One way to accomplish what you're describing: include the feature requests in your board configuration. Then, associate these workload impacting feature requests to a unique Epic called "Pending Feature Requests" (so they're not at the bottom of the plan) and leave them unestimated and not assigned. Then, in Scenario B you can put estimates on them and see the impact to your schedule and workload.

-Jason Golden
Denver AUG Leader

Suggest an answer

Log in or Join to answer
Community showcase
Josh Frank
Posted Dec 01, 2017 in Portfolio for Jira

Portfolio for Jira: Share your tips!

The Portfolio for Jira team wants to hear from you. Share your top tips for building a great Portfolio for Jira plan for a chance to win some Atlassian swag.  Do you structure your teams i...

544 views 6 8
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot